The Council’s multi-million pounds Community Sports Facility at Parklea Playing Fields in Port Glasgow will be completed on schedule for the start of the new football season in summer 2012.
On Thursday morning I was given a tour of the development along with Regeneration Committee Convener Ronnie Ahlfeld.
The new £2.9 million pavilion is now wind and watertight and work is underway inside to install walls, vents and finishes. Work is also underway on the large £650,000 3-G all-weather pitch, which will satisfy Scottish Junior Football Association regulations and be suitable for American Football and rugby training.
Parklea is very much the jewel in the crown of our £23 million investment in leisure and it is exciting to think that it is so near to completion.